MAJOR INDUSTRIAL FREEZER/CHILL WAREHOUSE CLEARANCE IN KENT.
This project involved the complete removal of all insulated wall/ceiling panels, de-commissioning of condenser units (Certified to regulations), Electrical wiring re-structuring (Certified to regulations), all fixtures and fittings, also complete disassembly of pallet racking removal and disposal. Areas made good and clean to customers specifications.
Objective: to revert warehouse back to original condition enabling customer to re-let.
Customer was very satisfied on completion of project.